Milestones

Toshiba JSW Power Systems Private Limited Journey In India

1994

01. Commissioned one of most reliable thermal power plant in India as Toshiba EPC lead - UPRVUNL Anpara 2x500MW Thermal Power Plant

2008

03. Established Toshiba JSW Steam Turbine & Generator Pvt. Ltd, Chennai for manufacturing supercritical steam turbine and generators

2013

04. First ultra-mega power plant having 5x830 MW supercritical steam turbine for Coastal Gujarat Power Limited, Mundra, Gujarat

2014

05. Established EPC office of Toshiba JSW Power Systems Pvt. Ltd. (TJPS) at Gurugram, Haryana

2016

07. Toshiba JSW shipped first indigenous supercritical steam turbine & generator for Unit #2 of NTPC Kudgi, Karnataka 3x800 MW super thermal power project

2017

08. Toshiba JSW commissioned Unit #1 of Meja Urja Nigam Pvt. Ltd. (MUNPL) 2x660 MW supercritical thermal power plant at Meja, Allahabad, Uttar Pradesh

09. Commercial Operation for Unit #1 and Unit #2 of supercritical steam turbine & generator of NTPC Kudgi, Karnataka 3x800 MW super thermal power project

2018

10. Commercial Operation for Unit #3 of supercritical steam turbine & generator of NTPC Kudgi, Karnataka 3x800 MW super thermal power project

2019

11. Commercial Operation for Unit #1 of Meja Urja Nigam Pvt. Ltd. (MUNPL) 2x660 MW supercritical thermal power plant at Meja, Allahabad, Uttar Pradesh

12. Toshiba JSW commissioned Unit #1 of NTPC Darlipali 2x800 MW super thermal power project - indigenous supercritical turbine & generator at Jharsuguda, Odisha

2020

13. Commercial Operation for Unit #1 of supercritical steam turbine & generator NTPC Darlipali 2x800 MW super thermal power project - indigenous supercritical turbine & generator at Jharsuguda, Odisha

14. Toshiba JSW forayed into the digital and cyber physical world by offering various IOT solutions with state-of-art technologies and processes in maintenance, renovation & modernization of thermal plants, and in upgrading critical turbine components to improve efficiency and reduce related CO2 emissions

2021

15. Commercial Operation for Unit #2 of Meja Urja Nigam Pvt. Ltd. (MUNPL) 2x660 MW supercritical thermal power plant at Meja, Allahabad, Uttar Pradesh

16. Commercial Operation for Unit #2 of supercritical steam turbine & generator NTPC Darlipali 2x800 MW Super Thermal Power Project - indigenous supercritical turbine & generator at Jharsuguda, Odisha

2022

17. Commercial Operation for Unit #1 of 1x660MW Harduaganj ultra-supercritical thermal power project from UPRVUNL